The account holder applies. The SSEG application goes to the electricity department of whichever municipality bills the property, and the applicant line carries the name on the municipal account — not the installer's, not the electrician's. What the installer owns is the technical layer behind the form: the single-line diagram, the equipment datasheets, the inverter's NRS 097-2-1 test documentation, and the Certificate of Compliance that gets issued once the wiring is done and tested.
Sit at my kitchen table on the Tuesday before an installation and you will see how that split works in practice. There is a printed application form, a highlighter that has gone dry, and a WhatsApp thread open on the phone. The installer's admin has sent the form back with four fields circled. Three of them — applicant, installation address, municipal account number — are mine. The fourth is his: registered electrician details, registration number, signature on the technical annexure.
Nobody argues about that part. What gets muddled is everything after it.
Doing the running around is not the same as being the applicant
An installer can submit the application for you. Many do, and there is nothing wrong with it — you sign an authority, he carries the file to the counter or uploads it to the portal, and a reference number comes back. That is a courier job.
Being the applicant is a different thing. It means the municipality's counterparty in the whole exercise is you, because you are the person it bills, the person the meter is registered to, and the person who carries the consequences of an approval, a refusal, or a condition attached to either. If a meter change is ordered, it is ordered against your account. If the file is refused, the refusal is addressed to you.
So the first thing to check is boring: does the name on the application match the name on the municipal account exactly? Not roughly. If the account is in a spouse's name, or a parent's, or a trust's, or the landlord's because you rent, that mismatch is where files stall. Sort it out before anything is printed, not after a query letter arrives.
Ask this before the first bracket goes into the wall
The one question that changes the whole sequence is whether your municipality wants written pre-approval before installation, or whether it accepts the application after the system is up but before it is energised. Those are two different orders of operation, and they are not the same across metros.
Where I am, the file had to exist before commissioning; a completed installation was not accepted as a starting point. That is my experience of one electricity department. It is not a rule you can carry to the next town, and anyone who tells you they all do it the same way is guessing.
So ask, and ask in a way you can keep. An email from the electricity department, or a counter visit where you write down the date and the name of the person and walk away with a reference number, is worth more than a friendly go-ahead from someone who might be on leave when the query comes back. Verbal reassurance is not a document. It also does not survive staff changes, and municipal offices have staff changes.
The pack, and who carries which page
This is the part I keep coming back to, because it is where "we'll handle the application" quietly turns into nobody handling it. Every document in the submission has an owner, and the owner is not always the same person.
- The application form itself — the account holder. Your signature, your details, your account number.
- The single-line diagram — the installer or the registered electrician. It shows what connects where: the inverter, the changeover, the points in the distribution board, and where the generation ties into the installation.
- Equipment datasheets — the installer or the supplier. Make, model, ratings, and the numbers that must line up with what actually gets mounted on the wall.
- Inverter NRS 097-2-1 test documentation, and whether the model appears on the relevant approved listing — installer or supplier. This is the one that catches people out, because it is about the specific model, not the brand, and not the same model in a different firmware revision.
- The Certificate of Compliance under SANS 10142-1 — the registered electrician, and only him. It is issued after the work and the testing, so it cannot travel with an application that goes in before installation. Where a municipality asks for it up front, it is usually being asked for at a later stage of the same file.
- The meter work — the municipality executes it, but you request and accept it. It is your account that gets the new meter.
If you want one habit out of all this: before you sign anything, ask who owns each line on the list, and write the answer down next to the document name. You will catch the gap early, when it is a phone call, instead of late, when it is a month.
Approval and the meter are two separate queues
An approval letter is not always the end of it. It is often conditional — approved subject to the fitting of a bi-directional meter, or subject to a meter change, or subject to a settings change that limits what the system does at the point of connection.
That meter work is a municipal job with its own lead time, and it does not move at the pace of your installer, who is standing in your driveway with the tools packed because his side is finished. The gap between the system running and the connection being registered the way it should be is real, and you cannot compress it by phoning more often.
Until the meter question is settled, most hybrid inverters can be set to zero export or a limited export setting. That setting should be a deliberate decision you understand, not whatever the commissioning screen happened to be left on. And do not assume your monitoring app and the municipal meter are seeing the same thing. A meter that was never designed to watch power move the other way does not report it the way the graph on your phone suggests.
Why I would not install first
Occasionally a retrofit application goes through cleanly. It depends on the metro, on the age of the connection, and on the state of the file. That is exactly why you ask first instead of assuming.
The other path has a worse shape. You install, you apply afterwards, the application is refused on the basis that generation was connected without authorisation, and now you are arguing about something that is already bolted to the wall. Reversing that is not a matter of resubmitting a form. It can mean proving the system was isolated, or accepting conditions you would not have chosen, or dealing with a file that now has a mark against it. Waiting for a pre-approval letter is a much cheaper inconvenience.
What stays in my folder
Everything, in one place, dated.
The submitted form as a PDF. The version of the single-line diagram that was actually submitted, not the later revision. The inverter's make, model and serial number. The NRS 097-2-1 test report or listing reference that was sent in. The Certificate of Compliance. The approval letter and any conditions attached to it. Photographs of the meter before and after, with the readings visible. And every email, in a thread rather than scattered across a phone.
That folder exists because when someone new opens your file at the municipality, the paper trail is your memory. Rebuilding it later, from a WhatsApp history and a blurry photo of a serial plate, takes far longer than keeping it did.
The installer does the engineering. You do the applying. Two jobs, two different people holding them. Let him run the errands — just make sure the reference number comes back in your name.